GHI Corporation, a California corporation, has a six-person board. At a regular board meeting, only two directors attend. No notice was sent to any of the directors. The two attending call directors Alice and Bob and put them on a conference call. The four talk about the corporation buying Blackacre and then all agree to a resolution for GHI to buy Blackacre from Third Party. The Bylaws of GHI state that an action of the board requires the consent of a majority of the directors present at a meeting, and that a quorum is a majority of the authorized directors.
Select one:
a. the purchase is authorized because a quorum was present and a majority of those present approved the action.
b. the purchase is not authorized, since all real estate transactions require shareholder approval
c. the purchase is not authorized because prior written notice must be sent to each director
d. the purchase is not authorized because a quorum was not present at the board meeting
e. Two of the above are correct.

Answers

Answer 1

Answer:

a. the purchase is authorized because a quorum was present and a majority of those present approved the action.

Explanation:

going by the bye laws of GHI state, board action requires that majority of the members of the board are present and give consent in the meeting. here in this question, we have a 6 member board. Although only two of the board members are physically present, through conference call Alice and Bob increased the number to 2 when they joined in. Therefore the number of board members at this meeting is 4, then the requirement has been met. So since this 4 agreed to the purchase, it is authorized and valid since a quorum was present and a majority of them agreed to the action. option a is correct

Answer 2

The correct statement is a. the purchase is authorized because a quorum was present and, a majority of those present approved the action.

The quorum required by the Bylaws of GHI is for a majority of directors to be present, and in this case, four directors were present (two physically and two by conference call).

The Bylaws of GHI specify that every action of the directors should be supported by a majority present at a meeting. We can conclude that the purchase is authorized by the majority (100%).

Thus, the purchase of Blackacre by GHI is authorized.

Learn more about board of directors, quorum, and majority votes here: https://brainly.com/question/7985365


Related Questions

Project Management Practice ProblemBragg’s Bakery is building a new automated bakery downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed.
ACTIVITYPREDECESSORNORMAL TIME (WEEK)CRASH TIME (WEEK)EXPEDITING COST/WEEKA-963000BA853500CA15104000DB,C532000EC1062500FD,E215000
Hint: I have directly provided the crashing cost per unit time.
a. What is the normal project length?
b. What is the critical path in this project?
c. Which activity will you choose to crash first to reduce the duration of the project by one week?
d. What is the project length if all activities are crashed to their minimum?
e. What is the slack for activity D?

Answers

Answer:

a. The normal project length is 36 weeks.

b. The critical path in this project is A-C-E-F.

c. The activity that you choose to crash first to reduce the duration of the project by one week is E because it has the least expediting cost/week amongst A, C, E, F.

d. The project length if all activities are crashed to their minimum is 23 weeks.

e. The slack for activity D is 5 weeks.

Explanation:

a) The normal length of the project = completion time of last activity = 36 weeks.

b) The criteria for critical activity:

[tex]LC_{i} = ES_{i} ,\\LC_{j} = ES_{j} ,\\[/tex]

[tex]ES_j - ES_i = LF_j - LF_{i} =[/tex] duration of the activity

where ES = Earliest start time, EF = Earliest finish time , LC = latest completion time, LF = latest finish time ,

The suffix- i refers to the preceding node, suffix-j refers to the succeeding node.

activities satisfying above all criteria are A, C, E, F

therefore critical path is A-C-E-F.

c) To reduce the project duration by 1 week. we should choose to crash among critical activities A, C, E, F. thus we choose to crash activity E because it has the least expediting cost/week amongst A, C, E, F.

d) if we crash all the activities to their minimum, then the project length = sum of crash time of all critical activities

= [6 + 10 + 6 + 1]

= 23 weeks.

e) The slack of activity d = LS - ES = 34 - 29

= 5 weeks

The critical path is given in the diagram,

Other Questions
Project Management Practice ProblemBraggs Bakery is building a new automated bakery downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed. ACTIVITYPREDECESSORNORMAL TIME (WEEK)CRASH TIME (WEEK)EXPEDITING COST/WEEKA-963000BA853500CA15104000DB,C532000EC1062500FD,E215000Hint: I have directly provided the crashing cost per unit time.a. What is the normal project length?b. What is the critical path in this project?c. Which activity will you choose to crash first to reduce the duration of the project by one week?d. What is the project length if all activities are crashed to their minimum?e. What is the slack for activity D? 9 What is the volume of the cone below? * 267.95 in3 33.49 in3 133.97 in3 Why is the history of Psychology important??? Which of the following is an example of the geographic concept of space?O West Africa is a geographic region on the continent of Africa.In New York City, subway stops are placed five blocks apartChloe lives in a suburb west of Houston, Texas.Each province or territory of Canada has a capital city.The country of Kazakhstan is south of Russia. national anthem of india, chinaand brazil When we expand (2x + 1/2)^6, what is the coefficient on the x^4 term? On the image below, which is the correct answer? A boy pushes his little brother on a sled. The sled accelerates from rest to (4 m/s). If the combined mass of his brother and the sled is (40.0 kg) and (20 W) of power is developd, how long time does boy push the sled?16s300s15s23s Which energy store is increased when an object is heated? the only reason i know cardiants is because of mincraft PLEASE HELP!!!Write the factored form of the least common denominator needed to simplify this expression What is the observation of heating of iodine crystals 4.2 To buy a new car is not a very good investment. In the first year the car willdecrease in value by 25%.4.2.1If the car costs R200 000, what will it be worth after 1 year? Simplify the expression.... Segment [tex]$s_1$[/tex] has endpoints at [tex]$(3+\sqrt{2},5)$[/tex] and[tex]$(4,7)$[/tex]. Segment [tex]$s_2$[/tex] has endpoints at [tex]$(6-\sqrt{2},3)$[/tex] and[tex]$(3,5)$[/tex]. Find the midpoint of the segment with endpoints at the midpoints of [tex]$s_1$[/tex] and [tex]$s_2$[/tex]. Express your answer as [tex]$(a,b)$[/tex]. Simplify -4 + (-3) + 6. If the amplitude of a sound wave is increased by a factor of four,how does the energy carry by the sound wave in each time interval change? The Marked price of a jacket at a dealer's shop is 2400. The dealer allows a discount of 15% to the retailer. As the company's policies the marked price of the retailer should be the same as the dealer's marked price. What SP should the retailer fix for the jacket? What would its final price be if 10% VAT is imposed? What would be the actual gain of retailer?Ans 2280,2502,240 in a sale, normal prices are reduced by 10%nathalie bought a pair of shoes in the sale for 54what was the original price of the shoes What is the solution to the inequality x(x 3) > 0?