Answer:
Fixed Overhead Volume Variance $ 54 Favorable
Explanation:
Fixed Overhead Volume variance is the difference between the budgeted fixed overhead and applied fixed overhead.
Budgeted Fixed Overhead = $7,560
Applied Fixed Overhead = Standard Rate * Standard Hours
Standard Rate for Fixed Overhead = $7,560/2,800 = $ 2.7
Applied Fixed Overhead = $ 2.7*2,820= $ 7614
Fixed Overhead Volume Variance=Budgeted Fixed Overhead-Applied Fixed Overhead
Fixed Overhead Volume Variance= $7,560-$ 7614= $ 54 Favorable
If applied overhead is more than budgeted overhead it is favorable because it indicates that the budgeted overhead is within in the standard range.
During March 2020, Toby Tool & Die Company worked on four jobs. A review of direct labor costs reveals the following summary data. Actual Standard Job Number Hours Costs Hours Costs Total Variance A257 200 $4,000 210 $4,200 $200 F A258 450 10,350 430 8,600 1,750 U A259 300 6,390 299 5,980 410 U A260 110 2,090 103 2,060 30 F Total variance $1,990 U Analysis reveals that Job A257 was a repeat job. Job A258 was a rush order that required overtime work at premium rates of pay. Job A259 required a more experienced replacement worker on one shift. Work on Job A260 was done for one day by a new trainee when a regular worker was absent. Prepare a report for the plant supervisor on direct labor cost variances for March. (Round actual rate and standard rate to 2 decimal places, e.g. 10.50.)
Answer and Explanation:
The Preparation of report for the plant supervisor on direct labor cost variances for March is attached with the help of spreadsheet.
The Formula are as shown below:-
Actual per hour = Actual costs ÷ Actual number of hours
Standard per hour = Standard costs ÷Standard number of hours
Quantity variance = (Actual hours -Standard hours) × Standard Rate
Price variance = (Actual Rate - Standard Rate) × Actual Hour
Therefore if actual hours is lesser than Standard hours it will become favorable and if actual hours is higher than standard hours it will become unfavorable. In the similar way if actual rate is higher than standard rate then it will become unfavorable on the other hand if actual rate is lesser than standard rate then it will become favorable.
Ratios are generally calculated from historical data. Of what use are they in assessing
the firm’s future financial condition?
I would say by the firm calculating their reports from before it usually shows where the company should stand for tears to come
Explanation:
Suppose Mr. Lane just bought a share of BlueWind Co., a renewable energy startup. BlueWind promises to pay Mr. Lane $18 in dividends for one year and then the firm will shut down. Suppose that the liquidation value of the share is $3, and the rate of time preference is 5%. Then, according to the single-period dividend discount model, the present value of the cash payment received by Mr. Lane in one year would be
Answer:
The present value of the cash payment is $20
Explanation:
The present value of cash payment receivable by Mr Lane in one year's time is the today's equivalent amount of the dividend of $18 as well as the liquidation value of $3.
The present value is the total cash inflows multiplied by the discount factor
discount factor=1/(1+r)^n
where is the rate of time preference of 5%'
n is 1 i.e in one year's time
total cash inflows=$18+$3=$21
discount factor =1/(1+5%)^1=0.95238
present value of cash payment=0.95238*$21=$20
The accounting records of Kesswil Company provided the data below. Net loss ($40,000) Depreciation expense 12,000 Increase in salaries payable 11,000 Increase in accounts receivable 4,000 Decrease in inventory 4,800 Amortization of patent 700 Decrease in premium on bonds payable 500 Requirements: Determine the following: (1) Increase (decrease) in operating assets (net): (2) Increase (decrease) in operating liabilities (net): (3) Net cash flows from operating activities:
Answer:
Increase (decrease) in operating assets (net)* $800
Increase (decrease) in operating liabilities** $10,500
Net cash flows from operating activities ($16,000)
Explanation:
Kesswil Company
Statement of cash flows (extract)
Net loss ($40,000)
Add: Depreciation expense 12,000
Amortization of patent 700
Increase (decrease) in operating assets (net)* 800
**Increase (decrease) in operating liabilities** 10,500
Net cash flows from operating activities ($16,000)
Note:
Increase in accounts receivable (4,000)
Decrease in inventory 4,800
*Increase (decrease) in operating assets (net): 800
Increase in salaries payable 11,000
Decrease in premium on bonds payable (500)
**Increase (decrease) in operating liabilities 10,500
Piedmont Hotels is an all-equity company. Its stock has a beta of .94. The market risk premium is 7.5 percent and the risk-free rate is 3.3 percent. The company is considering a project that it considers riskier than its current operations so it wants to apply an adjustment of 2.5 percent to the project's discount rate. What should the firm set as the required rate of return for the project
Answer:
Required rate of return for the project = 9.7%
Explanation:
The risk-adjusted discount factor = cost of equity + the adjustment
Cost of equity can be calculated using the capital asset pricing model CAPM
Using the CAPM , the rate of return on equity can be determined as follows:
E(r)= Rf +β(Rm-Rf)
E(r) =? , Rf- 3.3%, Rm- 7.5%, β- 0.94
Cost of equity = Rf + β (Rm -Rf)
Cost of equity = 3.3% + 0.94×(7.5-3.3)= 7.248
The risk-adjusted discount factor= 7.248 + 2.5= 9.748
Required rate of return for the project = 9.7%
Moates Corporation has provided the following data concerning an investment project that it is considering:
Initial investment $ 250,000
Annual cash flow $ 119,000 per year
Expected life of the project 4 years
Discount rate 8 %
Click here to view Exhibit 13B-1 and Exhibit 13B-2, to determine the appropriate discount factor(s) using the tables provided.
The net present value of the project is closest to: (Round your intermediate calculations and final answer to the nearest whole dollar amount.)
Multiple Choice
$250,000
$144,128
$(131,000)
$(144,128)
Answer:
$144,128
Explanation:
The net present value is the present value of after tax cash flows from an investment less the amount invested.
NPV can be calculated using a financial calculator:
Cash flow in year 0 = $-250,000
Cash flow each year from year 1 to 4 = $119,000
I = 8%
NPV = $144,143
To find the NPV using a financial calacutor:
1. Input the cash flow values by pressing the CF button. After inputting the value, press enter and the arrow facing a downward direction.
2. After inputting all the cash flows, press the NPV button, input the value for I, press enter and the arrow facing a downward direction.
3. Press compute
I hope my answer helps you
Becton Labs, Inc., produces various chemical compounds for industrial use. One compound, called Fludex, is prepared using an elaborate distilling process. The company has developed standard costs for one unit of Fludex, as follows: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 2.50 ounces $ 22.00 per ounce $ 55.00 Direct labor 0.90 hours $ 16.00 per hour 14.40 Variable manufacturing overhead 0.90 hours $ 2.00 per hour 1.80 Total standard cost per unit $ 71.20 During November, the following activity was recorded related to the production of Fludex: Materials purchased, 14,000 ounces at a cost of $289,800. There was no beginning inventory of materials; however, at the end of the month, 4,050 ounces of material remained in ending inventory. The company employs 26 lab technicians to work on the production of Fludex. During November, they each worked an average of 150 hours at an average pay rate of $15.00 per hour. Variable manufacturing overhead is assigned to Fludex on the basis of direct labor-hours. Variable manufacturing overhead costs during November totaled $5,000. During November, the company produced 3,900 units of Fludex. Required: 1. For direct materials: a. Compute the price and quantity variances. b. The materials were purchased from a new supplier who is anxious to enter into a long-term purchase contract. Would you recommend that the company sign the contract
Answer and Explanation:
a. The computation is shown below:
Material price variance
= Actual Quantity × (Standard Price - Actual Price)
= 14,000 × ($22 - $289,800 ÷ 14,000)
= 14,000 × ($22 - $20.70)
= 14,000 × $1.30
= $18,200 favorable
Material quantity variance
= Standard Price × (Standard Quantity - Actual Quantity)
= $22 × (3,900 units × 2.5 - 14,000 ounces - 4,050 ounces)
= $22 × (9,750 - 9,950)
= $22 × 200
= $4,400 unfavorable
b. Yes the contract should be signed as it is the actual price i.e $20.70 is less than the standard price $22
Xerox Corporation is using a predetermined overhead rate of $22.30 per machine-hour that was based on estimated total fixed manufacturing overhead of $446,000 and 20,000 machine-hours for the period. The company incurred actual total fixed manufacturing overhead of $409,000 and 18,200 total machine-hours during the period. The amount of manufacturing overhead that would have been applied to all jobs during the period is closest to:
Answer:
$405,860
Explanation:
Data given
Predetermined overhead rate = $22.30
Actual machine hours = $18,200
The computation of manufacturing overhead applied is shown below:-
Manufacturing overhead applied = Predetermined overhead rate × Actual machine hours
= $22.30 × 182,00
= $405,860
Therefore for computing the manufacturing overhead applied we simply multiplied the predetermined overhead rate with actual machine hours.
Marquis Company estimates that annual manufacturing overhead costs will be $900,000. Estimated annual operating activity bases are direct labor cost $500,000, direct labor hours 50,000, and machine hours 100,000. Compute the predetermined overhead rate for each activity base. (Round answers to 2 decimal places, e.g. 10.50% or 10.50.) Overhead rate per direct labor cost enter percentages rounded to 2 decimal places % Overhead rate per direct labor hour $enter a dollar amount rounded to 2 decimal places Overhead rate per machine hour $enter a dollar amount rounded to 2 decimal places
Answer:
Basis Rate
Labour hour $18 per direct labour
Machine hour $9 per machine hour
Budgeted labour cost 180% of labour cost
Explanation:
Predetermined overhead absorption rate=
Estimated Overhead for the period/Estimated activity level
Labour hour basis
Estimated Overhead for the period/Estimated labour hours
= $900,000/50,000
=$18 per direct labour
Machine hour basis
Estimated Overhead for the period/Estimated machine hours
Overhead rate per machine hour = $900,000/100,000 hours
=$9 per machine hour
Direct labour cost basis
Pre-determined overhead rate = Estimated Overhead for the period/Estimated labour cost
=$900,000/($500,000)×100
=180 % of labour cost
Basis Rate
Labour hour =$18 per direct labour
Machine hour =$9 per machine hour
Budgeted labour cost 180% of labour cost
Blossom Co. leased machinery from Young, Inc. on January 1, 2020. The lease term was for 8 years, with equal annual rental payments of $5,800 at the beginning of each year. In addition, the lease provides an option to purchase the machinery at the end of the lease term for $1,500, which Blossom is reasonably certain it will exercise as it believes the fair value of the machinery will be at least $5,000. The machinery has a useful life of 10 years and a fair value of $43,000. The implicit rate of the lease is not known to Blossom. Blossom’s incremental borrowing rate is 9%. Prepare Blossom’s 2020 journal entries
Answer and Explanation:
The Journal entry is shown below:-
1. Right of use Dr, $35,743.93
To lease liability $35,743.93
(Being lease assets and lease liability is recorded)
Working note as attached using spreadsheet
Here we debited the right of use as it increased the assets and we credited the lease liability as it also increased the liability
2. Lease liability Dr, $5,800
To Cash $5,800
(Being payment on lease liability is recorded)
Here, we debited the lease liability as it decrease the liability and we credited the cash as it decreased the asset
3. Interest expenses Dr, $2,694.95
To Lease liability $2,694.95
(Being interest expenses is recorded)
Here we debited the interest expense as it increased the expenses and we credited the leased liability as it increased the liability
4. Amortization expenses Dr, $3,574.39 ($35,743.93 ÷ 10 )
To Right of use $3,574.39
(Being amortization expenses is recorded)
Here we debited the amortization expenses as it increase the expenses and we credited the right of use as it reduced the assets
Working Note
Interest expenses = (Lease liability - First lease payment) × Incremental borrowing rate
= ($35,743.93 - $5,800) × 9%
= $2,694.95
ASAP HELP ME PLEASE , GIVING BRAINLIEST TO CORRECT AWNSER
Answer:
A
Explanation:
Answer:
because people would have to have good contraptions in order to be able to make free choices
Explanation:
Southern Alliance Company needs to raise $70 million to start a new project and will raise the money by selling new bonds. The company will generate no internal equity for the foreseeable future. The company has a target capital structure of 60 percent common stock, 15 percent preferred stock, and 25 percent debt. Flotation costs for issuing new common stock are 12 percent, for new preferred stock, 9 percent, and for new debt, 2 percent. What is the true initial cost figure the company should use when evaluating its project ?
Answer:
$88,832,487.31
Explanation:
According to the scenario, computation of the given data are as follow:-
FT = flotation cost of new debt percent × target capital debt percent + flotation cost of new common stock percent × target capital common stock percent + flotation cost of new preferred stock percent × target capital preferred stock percent
= 0.02 × 0.25+ 0.12 × 0.60 + 0.09 × 0.15
= 0.005 + 0.072 + 0.135
= 0.212
Now
True initial cost
= $70 million ÷ ( 1 - 0.212)
= $70 million ÷ 0.788
= $88,832,487.31
Waterways puts much emphasis on cash flow when it plans for capital investments. The company chose its discount rate of 8% based on the rate of return it must pay its owners and creditors. Using that rate, Waterways then uses different methods to determine the best decisions for making capital outlays.
In 2017 Waterways is considering buying five new backhoes to replace the backhoes it now has. The new backhoes are faster, cost less to run, provide for more accurate trench digging, have comfort features for the operators, and have 1-year maintenance agreements to go with them. The old backhoes are working just fine, but they do require considerable maintenance. The backhoe operators are very familiar with the old backhoes and would need to learn some new skills to use the new backhoes.
The following information is available to use in deciding whether to purchase the new backhoes.
Old Backhoes New Backhoes
Purchase cost when new $90,000 $200,000
Salvage value now $42,000
Investment in major overhaul needed in next year $55,000
Salvage value in 8 years $15,000 $90,000
Remaining life 8 years 8 years
Net cash flow generated each year $30,425 $43,900
Required:
1. Evaluate in the following ways whether to purchase the new equipment or overhaul the old equipment. (Hint: For the old machine, the initial investment is the cost of the overhaul. For the new machine, subtract the salvage value of the old machine to determine the initial cost of the investment.)
a. Using the net present value method for buying new or keeping the old
b. Using the payback method for each choice. (Hint: For the old machine, evaluate the payback of an overhaul.)
c. Comparing the profitability index for each choice.
d. Calculate the internal rate of return for the new and old blackhoes.
e. Comparing the internal rate of return for each choice to the required 8% discount rate.
Answer:
Explanation:
Base on the scenario been described in the question,Hey, since there are multiple sub-parts posted, we will answer first three sub-parts. If you want any specific sub-part to be answered then please submit that sub-part only or specify the question number in your message.
2
Compute the net present value to make decision for buying the new Backhoes or keeping the old:
We can fine the calculations in the file attached below
On December 31, Westworld Inc. has the following equity accounts and balances: Retained Earnings, $50,500; Common Stock, $2,100; Treasury Stock, $3,100; Paid-In Capital in Excess of Par Value, Common Stock, $40,100; Preferred Stock, $8,100; and Paid-In Capital in Excess of Par Value, Preferred Stock, $4,100. Prepare the stockholders’ equity section of Westworld’s balance sheet. (Negative amount(s) should be indicated by a minus sign.)
Answer:
$101,800
Explanation:
Westworld Inc.
Stockholder's equity section
Paid in the capital:
Particulars Amount Amount
Common stock $2,100
Additional paid-in capital in excess of par value-Common stock $40,100
Total$42,200
Preferred Stock $8,100
Additional paid-in capital in excess of par value-Preferred Stock $4,100
Total $12,200
Total Paid-in capital $54,400
($42,200+$12,200)
Retained earnings $50,500
Total Paid-in capital and Retained earnings $104,900
($54,400+$50,500)
Less: Treasury stock $-3,100
Total Stockholder's equity $101,800
The value of the total stockholder's equity will be $101800.
The stockholders’ equity section of Westworld’s balance sheet will be calculated thus:
Common stock = $2100Add: Additional paid in capital = $40100Add: Preferred stock = $8100Add: Additional paid in capital for preferred stock = $4100Add: Retained earnings = $50500Less: Treasury stock = $3100Total stockholders equity = $101800Read related link on:
https://brainly.com/question/16447368
The MoMi Corporation’s income before interest, depreciation and taxes, was $2.7 million in the year just ended, and it expects that this will grow by 5% per year forever. To make this happen, the firm will have to invest an amount equal to 15% of pre tax cash flow each year. The tax rate is 30%. Depreciation was $330,000 in the year just ended and is expected to grow at the same rate as the operating cash flow. The appropriate market capitalization rate for the unlevered cash flow is 12% per year, and the firm currently has debt of $5 million outstanding. Use the free cash flow approach to calculate the value of the firm and the firm’s equity. (Enter your answer in dollars not in millions.)
Answer:
1. The value of the firm is $23,760,000
2. The value of the equity is $18.76m
Explanation:
In order to calculate the value of the firm we would have to use the following formula:
Value of firm = FCF1 / (r - g) = FCF0 x (1 + g) / (r - g)
Operating Cash Flows (OCF) = (EBITDA - Depreciation) x (1 - tax) + Depreciation
= (2,700,000 - 330,000) x (1 - 30%) + 330,000
= $1,989,000
Free Cash Flow (FCF) = OCF - Investment
We know that investment = 15% of EBITDA = 15% x 2,700,000 = 405,000
Current FCF = 1,989,000 - 405,000 = 1,584,000
Therefore, Value of the firm = 1,584,000 x (1 + 5%) / (12% - 5%) = $23,760,000
To calculate the value of equity we would have to use the following formula:
Value of equity = Value of Firm - Value of Debt = 23.76 - 5 = $18.76m
Answer:
Value of the firm $ 14550000.
Value of the firm's equity $ 11550000.
Explanation:
Cash flow from operations = $ 1785000 (1700000 + 5 % of 1700000).
Depreciation = $ 241500. (230000 + 5 % of 230000).
Taxable income = $ 1543500 (1785000 - 241500)
Net income (after tax) = 1543500 - 30 % of 1543500 = $ 1080450.
Cash flow from operations (after tax) = 1080450 + 241500 (Depreciation, being non cash expense). = $ 1321950.
Free cash flow available = Cash flow from operations (after tax) - Income from investment.
= 1321950 - (1700000 * 17 % * 1.05)
= 1321950 - 303450.
= $ 1018500.
Value of the firm = Free cash flow available / (Capitalization rate - Growth rate)
= 1018500 / (0.12 - 0.05)
= 1018500 / 0.07
= $ 14550000.
Value of the firm's equity = Total value of firm - Value of debt of firm
= 14550000 - 3000000
= $ 11550000.
Conclusion :-
Value of the firm $ 14550000.
Value of the firm's equity $ 11550000.
A financier plans to invest up to $500,000 in two projects. Project A yields a return of 9% on the investment of x dollars, whereas Project B yields a return of 17% on the investment of y dollars. Because the investment in Project B is riskier than the investment in Project A, she has decided that the investment in Project B should not exceed 40% of the total investment. How much should the financier invest in each project in order to maximize the return on her investment
Answer:
She should invest $300,000 in Project A, and $200,000 in Project B.
Explanation:
Solution
Since Project B yields a higher return, she should invest as much money as possible in it, which is 40% of the total investment or
or (0.40)($500,000) = $200,000
so
The remaining $500,000 - $200,000 = $300,000 should be invested in Project A.
Therefore, she should invest $300,000 in Project A, and $200,000 in Project B.
Whitmer Corporation is working on its direct labor budget for the next two months. Each unit of output requires 0.07 direct labor-hours. The direct labor rate is $9.00 per direct labor-hour. The production budget calls for producing 4,200 units in February and 4,700 units in March. Required: Prepare the direct labor budget for the next two months, assuming that the direct labor work force is fully adjusted to the total direct labor-hours needed each month. (Round "labor-hours per unit"
Answer:
Results are below.
Explanation:
Giving the following information:
Each unit of output requires 0.07 direct labor-hours. The direct labor rate is $9.00 per direct labor-hour. The production budget calls for producing 4,200 units in February and 4,700 units in March.
Direct labor budget of February:
Direct labor hours= 4,200*0.07= 294
Direct labor cost= 294*9= $2,646
Direct labor budget of March:
Direct labor hours= 4,700*0.07= 329
Direct labor cost= 329*9= $2,961
Stahlmaere Inc. is a start-up company that manufactures simple machines. It is interested in analyzing the profit from a new machine using Monte Carlo simulation. It wants to investigate the profit resulting from a selling price of $150 per unit. The setup and advertising costs are known to total $75,000. They assume that the demand for the product is normally distributed with a mean of 1500 units and a standard deviation of 100 units. The company estimates that the raw material cost per unit is uniformly distributed between $5 and $6. The labor cost per unit is assumed to follow a discrete uniform distribution from $12 to $16. A junior analyst has devised the following Excel spreadsheet that simulates a single scenario using the information given above: Selling price per unit = 150 Set up and advertising cost = 75000 Demand = =NORM.INV(RAND(),1500,100) Raw material cost per unit = =5+(6-5)*RAND() Labor cost per unit = =RANDBETWEEN(12,16) Profit = =(B1*B4)-B2-((B5+B6)*B4) Copy-and-paste the above information into cells A1:B8 of an Excel spreadsheet. Then use a data table to repeat the simulation 1000 times. From the simulation results, estimate Stahlmaere's expected mean profit. Understanding that simulation is random in nature and that your estimate is unlikely to match any of the answer choices exactly, choose the answer choice that is closest to the estimated mean profit.
A. $180,000
B. $50,000
C. $150,000
D. $90,000
E. $120,000
Answer:
$ 120,000
Explanation:
Formulas:
Cell Formula
B4 =NORMINV(RAND(),1500,100)
B5 =5+(6-5)*RAND()
B6 =RANDBETWEEN(12,16)
B8 =(B1*B4)-B2-((B5+B6)*B4)
B12 =AVERAGE(F3:F1002)
Enter formula = B8 in cell E2
and =RANDBETWEEN(12,16) in E3 copy down to E1002 (this represents labor cost)
To create the data table, select range E2:F1002
click Data tab > What-If Analysis in Data Tools group > Data Table > In the resulting dialogue box, enter B6 in the Column Input cell, and B1 in the Row Input cell.
Estimated mean profit = $ 121,445 this is closest to $ 120,000
THE ANSWER IS $ 120,000
Stiller Corporation incurred fixed manufacturing costs of $24,000 during 2015. Other information for 2015 includes: The budgeted denominator level is 2,000 units. Units produced total 1,500 units. Units sold total 1,200 units. Beginning inventory was zero. The company uses absorption costing and the fixed manufacturing cost rate is based on the budgeted denominator level. Manufacturing variances are closed to cost of goods sold. Operating income using absorption costing will be ________ than operating income if using variable costing.
Answer:
Operating profit using absorption costing will be higher by $3,600 than operating income if using variable costing.
Explanation:
The difference between profit under variable costing and under absorption costing is simply the value of the change in inventory.
Usually, a decrease in inventory would cause profit under absorption costing to be lower . This is so because cost of goods sold would become higher leading to a lower profit . And vice versa
Difference in profit = POAR × change inventory
Predetermined Overhead absorption rate(POAR)
= Estimated overhead/ estimated production unit
= $24,000/2,000 units = $12 per unit
Change in inventory = 1500 - 1200= 300 units
Difference in profit = 300 × $12 per unit = $3,600
Operating profit using absorption costing will be higher by $3,600 than operating income if using variable costing.
Never Forget Bakery purchased a lot in Oil City six years ago at a cost of $278,000. Today, that lot has a market value of $320,000. At the time of the purchase, the company spent $6,000 to level the lot and another $8,000 to install storm drains. The company now wants to build a new facility on that site. The building cost is estimated at $1.03 million. What amount should be used as the initial cash flow for this project?
Answer:
The amount that should be used as the initial cash flow for this project is $1,350,000
Explanation:
The amount to be used as the initial cash flow for the project comprises of estimated building cost of $1.03 million and the market worth of the lot now.
The cost six years ago of $278,000,the cost of leveling as well as the cost of installing the storm drains were long ago time and are not relevant now.
In a nutshell the cost of the new project is $1,350,000($1,030,000+$320,0000)
Northfield Casino is considering converting the Polsky Building at University of Akron into a state-of-the-art gaming parlor. This expansion project will require an initial outlay of $75,000,000 with a project life of five years. Cash flows from operating the new parlor are expected to be $25,000,000 every year for the next five years. The parlor will be sold for $50,000,000 at the end of five years. The project's required rate of return, or discount rate is 18%. Based on this information: The project's payback period is:______.
a. 2.25 Years.
b. 2.5 Years.
c. 2.75 Years.
d. 3 Years.
e. 3.2 Years.
Answer:
d. 3 Years.
Explanation:
Payback period calculates the amount of time it takes to recover the amount invested in a project from its cumulative cash flows.
Payback period = amount invested / cash flow
$75,000,000 / $25,000,000 = 3 years
I hope my answer helps you
In 2020, Marigold Corp., issued for $102 per share, 86000 shares of $100 par value convertible preferred stock. One share of preferred stock can be converted into three shares of Marigold's $25 par value common stock at the option of the preferred stockholder. In August 2021, all of the preferred stock was converted into common stock. The market value of the common stock at the date of the conversion was $30 per share. What total amount should be credited to additional paid-in capital from common stock as a result of the conversion of the preferred stock into common stock?
Answer:
$2322,000
Explanation:
The computation of amount credited to additional paid-in capital is shown below:-
Amount credited to additional paid-in capital = Issued per share × Number of shares) - (Number if shares × Preferred stock shares converted into three shares × Par value of common stock
= ($102 × 86,000) - (86,000 × 3 × $25)
= $8,772,000 - $6,450,000
= $2322,000
So, for computing the amount credited to additional paid-in capital we simply applied the above formula.
On November 1, 2018, Green Valley Farm entered into a contract to buy a $150,000 harvester from John Deere. The contract required Green Valley Farm to pay $150,000 in advance on November 1, 2018. The harvester (cost of $110,000) was delivered on November 30, 2018. The journal entry to record the contract on November 1, 2018 includes a Group of answer choices a) credit to Accounts Receivable for $150,000 b) credit to Sales Revenue for $150,000. c) credit to Unearned Sales Revenue for $150,000. d) debit to Unearned Sales Revenue for $150,000.
Answer:
d) debit to Unearned Sales Revenue for $150,000
Explanation:
Green Valley Farm Journal entry
Dr Unearned Sales Revenue 150,000
Cr Sales Revenue150,000
Dr Cost of Goods Sold 110,000
Cr Inventory110,000
Therefore the journal entry to record the contract on November 1, 2018 is debit to Unearned Sales Revenue for $150,000
University Car Wash built a deluxe car wash across the street from campus. The new machines cost $267,000 including installation. The company estimates that the equipment will have a residual value of $24,000. University Car Wash also estimates it will use the machine for six years or about 12,000 total hours. Actual use per year was as follows: Year Hours Used 1 3,000 2 1,200 3 1,300 4 2,700 5 2,500 6 1,300 Required: 1. Prepare a depreciation schedule for six years using the straight-line method. (Do not round your intermediate calculations.)
Answer and Explanation:
According to the scenario, computation of the given data are as follow:-
Straight Line Depreciation = (Cost - Residual Value) ÷ Useful Life
= ($267,000 - $24,000) ÷ 6
= $40,500
Year Opening book value Dep. Accumulated dep. Closing book value
1 $267,000 $40,500 $40,500 $226,500
2 $226,500 $40,500 $81,000 $186,000
3 $186,000 $40,500 $121,500 $145,500
4 $145,500 $40,500 $162,000 $105,000
5 $105,000 $40,500 $202,500 $64,500
6 $64,500 $40,500 $243,000 $24,000
Mobility Partners makes wheelchairs and other assistive devices. For years it has made the rear wheel assembly for its wheelchairs. A local bicycle manufacturing firm, Trailblazers, Inc., offered to sell these rear wheel assemblies to Mobility. If Mobility makes the assembly, its cost per rear wheel assembly is as follows (based on annual production of 2,000 units): Direct materials $ 26 Direct labor 53 Variable overhead 21 Fixed overhead 49 Total $ 149 Trailblazers has offered to sell the assembly to Mobility for $110 each. The total order would amount to 2,000 rear wheel assemblies per year, which Mobility's management will buy instead of make if Mobility can save at least $20,000 per year. Accepting Trailblazers's offer would eliminate annual fixed overhead of $38,500. Required: a. Prepare a schedule that shows the total differential costs. (Select option "higher" or "lower", keeping Status Quo as the base. Select "none" if there is no effect.)
Answer and Explanation:
The preparation of the total differential cost schedule is presented below
Schedule showing statement of total differential cost
Particulars Make the wheels Buy from trailblazers Differential cost
Offer of trailblazer $220,000 $220,000 Higher
(2000 × $110)
Material cost $52,000 $52,000 Lower
($26 × 2000)
Labor cost $106,000 $106,000 Lower
($53 × 2000)
Variable overhead $42000 $42,000 Lower
($21 × 2000)
Fixed overhead $98000 $59,500 $38,500 Lower
($49 × 2000) ($98,000 -$38,500)
Total cost $298,000 $279,500 ($18,500) Lower
By adding the total cost we can get the making cost, buying cost and differential cost
During its first year of operations, a company granted its employees vacation privileges and pension rights estimated at a cost of $23,125 and $15,073, respectively. The vacations are expected to be taken in the next year, and the pension rights are expected to be paid in the future 5-30 years. What is the total cost of vacation pay and pension rights to be recognized in the first year
Answer:
$38,198
Explanation:
Recognization principle state that the total amount paid in the first year will be the sum of the amounts given as a whole which will inturn be considered as paid for the employees.
Therefore for the first year, the vacation pay and the pension right will be :
$23,125 +$15,073
=$38,198
Therefore the total cost of vacation pay and pension rights to be recognized in the first year will be $38,198
During April, the production department of a process operations system completed and transferred to finished goods 18,000 units that were in process at the beginning of April and 90,000 units that were started and completed in April. April's beginning inventory units were 100% complete with respect to materials and 40% complete with respect to labor. At the end of April, 30,000 additional units were in process in the production department and were 100% complete with respect to materials and 60% complete with respect to labor. The beginning inventory included materials cost of $107,000 and the production department incurred direct materials cost of $329,000 during the month. Compute the direct materials cost per equivalent unit for the department using the weighted-average method
Answer:
Cost per equivalent unit of materials = $3.16
Explanation:
Under the weighted average method of valuation, to account for completed units, it is assumed that the entire degree of work required is done in the period under consideration. So there is no separation of the completed units into opening inventory and fully worked.
Cost per equivalent unit = cost / total equivalent units
Total units completed and transferred out= 18,000 + 90000= 108,000
Items Unit Equivalent unit
Completed units 108,000 100% × 108,000 = 108,000
Closing inventory 30,000 100% × 30,000 = 30,000
Total equivalent unit of material 138,000
Cost per equivalent unit = Total cost/Total equivalent unit
= (107,000 + 329,000) /138,000 units
= $3.16
On May 1, 2020, Riverbed Inc. entered into a contract to deliver one of its specialty mowers to Kickapoo Landscaping Co. The contract requires Kickapoo to pay the contract price of $990 in advance on May 15, 2020. Kickapoo pays Riverbed on May 15, 2020, and Riverbed delivers the mower (with cost of $648) on May 31, 2020. (a) Prepare the journal entry on May 1, 2020, for Riverbed. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts.)
Answer and Explanation:
The journal entries are shown below:
On May 1
No journal entry is required as the Riverbed Inc entered into a contract for delivering of the specialty mowers to Kickapoo Landscaping Co which do not required any kind of entry because there is no need to record the entry that contains any type of contract entered
Okun's law states that
a. a change in the output gap occurs with a change in the rate of unemployment that is smaller in magnitude and in the opposite direction.
b. a change in the output gap occurs with a change in the rate of unemployment that is larger in magnitude and in the opposite direction.
c. inflation causes a decrease in the value of money held by the public.
d. the government may temporarily suspend citizens' rights during periods of hyperinflation in an attempt to maintain security and stability.
Answer:
C, I think is the answer.
Explanation:
Poe Company is considering the purchase of new equipment costing $80,000. The projected net cash flows are $35,000 for the first two years and $30,000 for years three and four. The revenue is to be received at the end of each year. The machine has a useful life of 4 years and no salvage value. Poe requires a 10% return on its investments. The present value of $1 and present value of an annuity of $1 for different periods is presented below. Compute the net present value of the machine.Periods Present Valueof $1 at 10% Present Value of anAnnuity of $1 at 10%1 0.9091 0.90912 0.8264 1.73553 0.7514 2.48694 0.6830 3.1699
Answer:
NPV = $23,773.65
Explanation:
Net present value is the present value of after tax cash flows from an investment less the amount invested.
NPV can be calculated using a financial calculator:
Cash flow in year 0 = $-80,000
Cash flow each year for 1 and 2 = $35,000
Cash flow each year for 3 and 4 = $30,000
I = 10%
NPV = $23,773.65
To find the NPV using a financial calacutor:
1. Input the cash flow values by pressing the CF button. After inputting the value, press enter and the arrow facing a downward direction.
2. After inputting all the cash flows, press the NPV button, input the value for I, press enter and the arrow facing a downward direction.
3. Press compute
I hope my answer helps you